How can we take action against a pool building company who have not actually breached contract?

Question Details: The contract was signed 4 months ago but permit application wasn't submitted by until about 6 weeks later. Dig started a month ago and since then they have turned up 4 days, usually with at least 10 days in between. They are behind schedule? Can we put each payment which we contractually owe after a certain job in escrow so that they don't get it until they have completed satisfactorily?

Jonathan Pollard / Pollard LLC Answered 9 months ago This attorney is licensed in Florida View Attorney Profile